Interconnection queue position: how the line is ordered
TL;DR
Your interconnection queue position is your ordered place in the line of projects waiting to connect to the electric grid, assigned when you file an interconnection request. It matters because it influences how much of the grid-upgrade cost you carry and how soon your studies run — but even a good position typically still means a multi-year wait, which is why large loads increasingly bypass the queue with on-site generation.
On this page
What “queue position” means
You cannot connect a power plant — or a gigawatt-scale data center — to the grid without the grid operator studying the request first. When you file an interconnection request, the operator assigns it a queue number: your ordered place in the line of projects waiting to be studied and approved.
That position is more than a ticket. The operator studies each request to determine how the new project affects power flows, what transmission upgrades the grid needs to accommodate it, and who pays for them. Where you sit in the line historically shaped both when your studies run and how much of the upgrade cost lands on you versus the projects around you.
How the order is actually decided
For decades the queue ran first-come, first-served. Projects were studied serially, roughly in the order they arrived, and each project’s position — and its cost allocation — depended on everything ahead of it. That created a brittle chain: when a project near the front withdrew, the studies behind it often had to be redone, cascading delays down the whole line.
That model is being replaced. Under FERC Order 2023 (issued in 2023, with regions transitioning through roughly 2024–2025), the process shifts to first-ready, first-served cluster studies. Instead of studying requests strictly one-by-one by arrival, the operator groups projects in a geographic area into a cluster and studies them together, allocating shared upgrade costs across the group. The reform also adds readiness and commercial milestones and financial deposits so speculative projects can’t hold a good position indefinitely and clog the line.
The regional grid operators run their own variants of this reform: PJM, MISO, CAISO, and ERCOT each administer queue processes tuned to their footprint, so the exact rules for a given position depend on which ISO/RTO territory the project sits in.
Why a good position still means a multi-year wait
Even a strong queue position does not buy a fast connection. The line moves slowly for structural reasons: many projects need transmission upgrades that are expensive and slow to build, withdrawals upstream can trigger restudies, and the sheer volume of requests overwhelms the capacity to study them.
The scale is the real story. Berkeley Lab’s Queued Up analysis found more than 2,000 GW of generation and storage capacity waiting in the nation’s queues — more than the entire existing US power fleet — with the median project taking about four to five years from request to commercial operation (LBNL). Moving up a few places in a line that long changes the finish date by months, not years.
The escape hatch for AI and data-center loads
For an AI operator, queue position is often beside the point. If you need power in 2027, it does not matter whether you are near the front of a line that clears in 2030 — the timeline still misses the build schedule.
This is why large loads increasingly bypass the queue entirely with behind-the-meter generation: building power on-site, on the customer side of the utility meter, so the facility runs without waiting for a grid connection. It converts a queue-and-permitting problem into a procurement-and-construction one — the trade being that you now own the generation and its timeline. Fast-start gas turbines are the common way to energize a site while a grid connection or larger plant is still years out.
Frequently asked questions
How is interconnection queue position determined?
It is assigned by the grid operator when you file an interconnection request — historically as a first-come, first-served queue number based on arrival order. Under FERC Order 2023, most regions are moving to first-ready, first-served cluster studies, which group nearby projects and study them together rather than strictly by the order they arrived, while requiring readiness milestones and financial deposits to hold a spot.
Can you improve or move up your queue position?
Not by simply asking to jump the line — position is set by your request date and the operator’s process. In practice, projects advance because others ahead of them withdraw, and the queue-reform rules now push out speculative projects that miss readiness or deposit milestones. Meeting those milestones keeps your position; it does not leapfrog you past ready projects ahead.
Does a better queue position guarantee a faster connection?
No. Even near the front of the line, the connection date is gated by transmission upgrades, restudies triggered when other projects drop out, and the volume of requests the operator must work through. With the median project waiting about four to five years nationally, a strong position shifts the timeline by months, not years — which is why loads that need power quickly turn to on-site generation instead.
Related
What is an interconnection queue?
An interconnection queue is the formal waiting line of projects — power plants, storage, and increasingly large loads like data centers — seeking grid interconnection, the studied permission to connect to the electric grid. Every request must be modeled for its impact on the system before approval, and the backlog has grown so large that the median project now waits about four to five years.
Read →What is behind-the-meter power?
Behind-the-meter (BTM) power is electricity generated and consumed on-site — on the customer side of the utility meter — rather than drawn from the grid. For large loads like AI data centers facing multi-year grid interconnection waits, BTM generation is increasingly the primary way to energize a site instead of a backup.
Read →Why are gas turbines sold out?
Gas turbines are effectively sold out because data-center power demand has outrun a manufacturing base that scaled down for years. Heavy-frame turbine slots are booked toward the end of the decade, lead times have stretched to several years, and buyers now reserve capacity far in advance — which is why fast-start aeroderivative units have become the go-to bridge.
Read →Last updated