GE Vernova
GE LM6000 PD (DLE) Aeroderivative Gas Turbine — 41 MW
Used and surplus GE LM6000 PD DLE aeroderivative gas turbine for sale — the dry-low-emissions ~41 MW variant for permit-constrained sites, with a refurbished engine at 10,000–14,000 hours since refurbishment and a professional borescope from the last 12 months on file.
Used and surplus GE LM6000 PD aeroderivative gas turbine with Dry Low Emissions (DLE) combustion available for sale through Pantheon. The PD is the lean-premix member of the LM6000 family: it reaches its NOx limit without water or steam injection, which is what makes it the practical LM6000 choice where an air permit or water supply constrains the site. The current lot is a 1997–2001 package whose engine was refurbished in 2019–2021 and has run 10,000–14,000 hours since — the package figure is higher, and it is the engine number that reflects remaining life. It carries a professional borescope inspection from the last 12 months, performed to the OEM maintenance schedule and compared against the previous cycle: low- and high-pressure compressors, combustor and fuel nozzles, high-pressure turbine nozzles and turbine sections were all recorded as serviceable, documented in a ~40-page report with photographic records, engine identification and history, and running data. Two things a buyer should know up front: the report leaves one actuation-system item to be investigated and cleared before operation, and four routine inspections were deferred at that outage for time. Closing the open item and completing the deferred inspections can be made a condition of sale, and a written reconciliation of engine and package hours is in hand. As-is or refurbished-with-60 Hz-conversion routes. Exact rating, hours, and configuration confirmed at quote.
Specifications
| Type | Aeroderivative gas turbine (LM6000 PD, twin-spool) |
|---|---|
| Output (simple cycle) | ~41 MW ISO |
| Efficiency (simple cycle) | ~41% |
| Combustor | DLE (dry low emissions, lean-premix) · no water/steam injection |
| Frequency | As-is at current site frequency · 60 Hz conversion included in refurbished scope |
| Fuel | Natural gas |
| Start time | Fast-start (~10 minutes) |
| Vintage | 1997–2001 package · engine refurbished 2019–2021 |
| Operating hours | 10,000–14,000 engine hours since refurbishment (package hours higher, reconciled in writing) |
| Inspection | Professional borescope within the last 12 months, to OEM schedule, vs prior cycle · ~40-page report with photographs · sections serviceable |
| Open items | One actuation-system item to clear before operation · four routine inspections deferred — can be a condition of sale |
| Scope options | As-is · or refurbished (bearings, gearboxes, controls, BOP) + 60 Hz conversion |
| Delivery | On order placement · as-is ~3–6 months · refurbished + conversion ~8–12 months |
| Offer window | Lot listed through 2026-12-31 · availability re-confirmed at quote |
| Condition | Used and surplus · refurbished engine, current borescope on file |
Specifications shown are headline figures. Confirm full configuration details when you request a quote.
Last updated
Request a quote for GE LM6000 PD DLE Aeroderivative Gas Turbine
Tell us your requirements and we'll get back to you with availability and pricing.
or reach us directly at